Transport strategy for dual landscape during Technical Upgrade EHP7

$
0
0

Hi Experts,

 

We are planning to perform a technical upgrade of our ECC system to latest EHP7 from EHP4 so plan is to use dual landscape like below

 

Prod Support

D1 --> Q1 --> P1

 

Project

D2 --> Q2 --> D1 --> Q1 --> P1

 

My question is when transports from Q2 moves into D1, can we create transport of copies to include D2 transports to retain the version management and move the newly created transports from D1 --> Q1 --> P1 ?

 

Another question is when D1 is upgraded to EHP7 then it will be not be available for the production support. In this situation how should we manage the production support ?

 

Regards,

Krishna